Lahan 3.412 M2 Belum Dibebaskan untuk Waduk Pondok Ranggon 1
.
photo istimewa - Beritajakarta.id

Land Buying Obstructs Pondok Ranggon 1 Reservoir Construction

The construction of Pondok Ranggon 1 and 2 Reservoir is targeted to complete by this year. In fact, not all land are already bought.

3,412 meter square is divided into 16 lots. Seven of them have buildings above it

Pondok Ranggon 1 reservoir leaves 16 land lots by 3,412 meter square. The remaining 2,371 meter square are being inventoried.

Pondok Ranggon Urban Village Head, Mahpuz MZ, admitted the land buying process for Pondok Ranggon 1 has been started since 2006 ago. It is planned that the reservoir has total width by 11.5 hectares.

Rambutan 1 Reservoir Project Needs Additional Equipment

“3,412 meter square is divided into 16 lots. Seven of them have buildings above it,” he said, Thursday (9/22).

Asep Setia Permana, Jakarta Staff of River and Beach for East Flow for Dept. of Water Management, said his side is cooperating with Mabes TNI to deploy the heavy equipment. It is impossible to deploy the equipments via settlement road.

“The only access is via Mabes TNI,” he said.

Linked News
Popular News indeks
  1. Jakarta and Lampung Collaborate to Launch Lampung-in App

    access_time15-06-2025 remove_red_eye446 personDessy Suciati
  2. City Ready to Support Railway Transportation System in Bali

    access_time13-06-2025 remove_red_eye409 personBudhi Firmansyah Surapati
  3. Jakarta Future Festival 2025: Invitation to Contribute Developing Jakarta

    access_time12-06-2025 remove_red_eye396 personAldi Geri Lumban Tobing
  4. City Council Fractions Deliver General Views on 2024 APBD Accountability

    access_time16-06-2025 remove_red_eye352 personFakhrizal Fakhri
  5. Cloudy Morning, Rainy Afternoon this Tuesday, BMKG Says

    access_time17-06-2025 remove_red_eye292 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik